Guidelines
Guidelines for Purchasing Commodities
$20,100 and under
Enter a requisition into the SAP system at least three weeks before commodity is needed.
Bids will be solicited if we believe we can save you money by doing so.
$20,100.01 and over
Enter a requisition into the SAP system at least six weeks before commodity is needed.
Sealed bids are required for purchases with a value of $20,100.01 or more.
$35,000 and over
Enter a requisition into the SAP system at least six to eight weeks before the commodity
is needed. Commodities with a purchase value of $35,000 or greater require the Board
of Trustees' Finance Committee approval before the purchase order can be issued. This
can add up to 30 days lead time to the purchasing process depending on when the committee's
monthly meeting is scheduled.
Guidelines for Purchasing Services
$5,000 and under
Enter a requisition into the SAP system at least three weeks before the service is
needed. Purchasing will then transfer it to a purchase order. The purchase order will
then be sent to the vendor via FAX, mail, etc.
$5,000.01 to $20,100.00
Enter a requisition into the SAP system at least four weeks before the service is needed. Purchasing will create a Service Purchase Contract (SPC). NOTE: A fully approved SPC must be in effect BEFORE the services commence. SPCs require approval by the university's legal counsel. Drafting the SPC and getting legal council approval adds two weeks to the purchasing process. The university cannot pay for services costing more than $5,000 that do not have an SPC in place before the start of the service.
$20,100.01 and over
Enter a requisition into the SAP system at least six weeks before service is needed.
Sealed bids are required for purchases with a value of $20,100.01 or more require
Office of Attorney General review and approval prior to the start of the service.
$35,000 and over
Enter a requisition into the SAP system at least six to eight weeks before the service
is needed. The provisions of a $35,000 and over service purchase need to be completed
along with the Board of Trustee's Finance Committee approval before the SPC can be
issued.