Key 93 List 06-07
PEC Approved 1-07 to Include Transformer for Multiple Faciliries
Fund Sources
Key-93 06-07 Based on average of past five of six years * $686,542
Univ. Supplement Assumes supplement will not be available $0
Carry-Over 05-06 Based on 05-06 Balance a/o 8-15-06 $674,546
Maximum Amount Available $1,361,088
Project
Cost Cumulative
Egbert Restore Masonry, Repl/Rpr Gutters, Paint Facia/Cornice, Rpr Roof  $196,838 $196,838
Chapel Restore Masonry & Windows, Replace Roof $141,445 $338,283
Multi Replace Transformer located @ Givan Hall $76,950 $415,233
Still Hall Replace Windows (existing 28 yrs old) $232,964 $648,197
Frame/Rhoades Repair Steps - Frame/Rhoades $24,800 $672,997
Stevens Hall Clean, Restore, & Seal Masonry $50,674 $723,671
Special Ed Replace Roof, Restore Masonry $100,987 $824,659
Total - All Recommended Projects $824,659
Net Available a/o 12-1-06 After Funding Recommended Projects $536,429
Received through  4-10-07** $415,234
Total Available for Projects a/o/ 4-10-07 for 07-08 Program $951,663
* Funding during one of the six years was unusually low, due to a legislatively imposed 50% 
funding cut.  Consequently, that specific year was removed from the average.  
** Funding was interrupted in April, 2007, with no assurance at the time that follow-on funding 
would be forthcoming.  FY-07-08 Program was developed to accommodate this scenario.