2006-07 Update of the Clarion University Facilities Master Plan

April 16, 2007

 

Process

 

Each year, Pennsylvania State System universities provide a capital request detailing their major facility needs.  These are supported by an update to the University’s Facilities Master Plan outlining significant changes in the conditions and assumptions of the University’s facilities, most significantly for 2007 the completion and approval of the University’s Strategic Plan. 

 

The Facilities Master Plan, like the Strategic Plan, had to reflect budget constraints and challenges.  Equally important however were changes in the auxiliary sector which had major implications, at minimum, for the pace of renovation to E&G buildings and underlying infrastructure.

 

A.  Assumptions, Themes, and Space Needs

 

In constructing the April 1998 Master Plan, the committee and consultant worked with a number of initial assumptions and themes.  While the University has made some striking improvements, the underlying conditions in 1998 still determine many of today’s decisions.

 

1.      The landscape appearance is currently diminished by converted fragmented collections, domestic residential or utilitarian buildings, and mismatched furnishings handrails and guardrails which need to be upgraded to current ADA standards.

 

2.      While the features provide panoramic views and natural settings, the steep slopes impede vehicle and pedestrian flow, are difficult to maintain, and provide few level building sites.

 

3.      New facilities should link people and functions, define open spaces, and establish visual, programmatic, and physical connections.  They should be incremental and independent of other changes. 

 

4.      Academic offices & support facilities should be close to classroom space.  Faculty should be provided with private office space and adequate support space. 

 

5.      Academic uses should be clustered in one education core area and administrative departments should be located where they can best serve their student, faculty, staff, or public constituents. 

 

6.      To enhance community relations the Main Street face of campus should be upgraded, the natural setting where University land connects with the river should be preserved and enhanced, and campus expansion should be limited.

 

This qualitative analysis was buttressed by a quantitative analysis of the University’s space needs in the context of State System of Higher Education based on a projection of 5,900 FTE enrollment (Clarion Campus) for the year 2016.

 

  1. The University has a total of 54 buildings with 1,087,486 assignable square feet (asf); 49 of the buildings are on the Clarion campus and 5 are on the Venango campus.  Academic and support use aacounts for 66% of this area, 31% is used for student residences, dining, and recreational purposes and 3% of the space supports facilities maintenance needs. 

 

  1. The State System specifies criteria for ideal allocation of space.  The current surplus of 10,823 asf of classroom space would be reduced to 5,198 asf with the demolition of the Peirce Science Center.  The Becht Hall renovation would further reduce this surplus to 1,919 asf. 

 

  1. In 2005 classrooms were only used 5.2 hours/day.

 

  1. Critical shortages were identified for library, food service, and athletic/recreational space. Research lab space shortfalls were also identified but may not be support by State System measurement.

 

B.  Near-Term Issues

 

Since the Facilities Master Plan was finalized in 1998, a number of elements under consideration have been completed.  The list includes the renovation of Founders Hall, Harvey Hall, Keeling, Carlson Library, and the newly-constructed Recreation Center.  These completed projects have allowed Founders to accommodate the departments of History and Political Science, Sociology, and Philosophy, and office of the Dean of Arts & Sciences; Davis to house English and Modern Languages; Harvey to house Psychology; Keeling to house the Communication Sciences and Disorders program and the Health Center; and Carlson to house the Library Science Department and all library functions.  Additionally, the Center for Advancement at Clarion University was constructed, allowing vacation of Haskell House.

 

Even with the successes cited above, the Master Plan diverges from the current status of facilities in a number of ways.  First, Becht Hall has been listed as a potentially funded System capital project for 2008.  However, this delays relocation of the Academic Enrichment Center to this ostensibly permanent location until that time.  Second, with the commissioning of Reinhard Villages, Campbell Hall was vacated after Spring 2004 in accordance with the Residence Hall Plan.  Consequently, Commonwealth approval was obtained for demolition, and the Academic Enrichment Center moved from Campbell to the first floor of Ralston Hall as students began the transition to Reinhard Villages.  Funding has now been allocated for the demolition of Campbell Hall, and planning is underway.  The next step will be to replace Campbell with a parking deck and expand the ground-level parking near Campbell.

 

While this addresses the needed relocation of the Academic Enrichment Center, the delay in Becht’s completion impacts Financial Aid, Accounts Receivable, and Accounts Payable, all part of the planned Becht “one-stop shopping” concept.  Moreover, the one-stop shopping concept itself needs a fresh look in light of a recent Enrollment Management study and changes in the student service field. 

 

Early in discussions of the Master Plan update, it became obvious to members of the update committee that separate groups needed to examine one-stop shopping to see if the original concept still provided the most desired method of improving student services.  Essentially, the Facilities Master Plan must address one-stop shopping in the context of the University’s academic plan and its strategic plan.  As an interim measure, a virtual one-stop center was set up as an extension to the University’s website, and an entrée to an actual one-stop shopping facility.

 

The Master Plan originally advocated Alumni and Advancement’s move from Haskell House to Moore Hall and a move of the University Relations Department from Alumni House to Moore as well.  Funding considerations and the inability of Moore Hall to accommodate the functions and the people therein, led to postponement of these relocations.   Subsequently however, funding for the replacement of the Science and Technology Center and the expansion on the south side of campus suggested that a new free-standing alumni and advancement building at the corner of Corbett and Greenville Avenues would be preferable.  Accordingly, a new building to house the Center for the Advancement of Clarion University was constructed and occupied in 2004.

 

Although this construction accommodated the space and accessibility needs of Alumni and Advancement, the master plan committee noted that these moves left behind the University Relations Department.  According to the Master Plan, this Department would need to be relocated to facilitate the demolition of both Haskell and Alumni Houses.  Given the proximity of these structures to underground lines and piping, and the need to accommodate potential new on-campus student residences, implementation of that recommendation seems more proximate and University Relations will move to Ralston awaiting completion of the Becht renovation.

 

 


C.  The Near-Term Plan (2004-2009)

      (Refer to Tables 5.2-1 for accompanying summary table.)

 

Consolidating the above into an updated Master Plan begins with shifting the timelines for near-term, mid-term, and long-term five years out, starting with the current year, 2005. 

 

As noted above, the new building on Corbett Street for the Center for the Advancement of Clarion University allowed the functions of Alumni Affairs and Development to be moved from their current location at Haskell House.  Both Alumni and Haskell House will be demolished as one project allowing lower demolition costs and securing utilities concurrently.

 

Minimal renovations at the Ceramics Studio and the Foundry make these facilities serviceable for classes.  However, space needs for Ceramics, Sculpture, and other art activities not currently located in Marwick-Boyd continue to be assessed.  While we have sought opportunities for leased space for these programs, current budget constraints have precluded this option while the long-term desire to consolidate these programs in Marwick Boyd still holds true.  To this end, a capital project for the renovation and expansion of Marwick Boyd was approved in Act 40 of 2004 and now awaits placement in the PASSHE funding plan.  Recent concerns about the structural envelope of the Tippin Gymnasium facility and the high ongoing operational costs of maintaining it lead us to make this facility a higher capital funding priority at this time. 

 

A feasibility plan will be necessary to assess the need for possible near-term, renovations to Tippin Gymnasium and the Marwick-Boyd Fine Arts Center.  This is particularly important in the case of Marwick, if funding for its renovation and addition is delayed. 

 

Academic Enrichment Center has moved into the first floor of Ralston Hall, with other Academic Enrichment Center grant programs now moved from the modular building adjacent to the Science and Technology Center parking lot to the second floor of Ralston to facilitate Science and Technology Center construction.

 

D.  Mid-Term Issues

 

Two key recommendations of the original master plan, relocation of student services to Becht and construction of a parking deck have been re-considered in light of favorable alternatives.  Becht has been discussed above in the near-term section, and the parking alternative is provided in a separate parking plan attached as Appendix B.

 

The renovation of Becker Hall to provide more usable space was mentioned in the mid-term section of the original Master Plan (now the near-term).  To date this renovation has not been programmed in detail, and the future needs of Becker need to be defined in a feasibility study, particularly in light of increased activity on the south end of campus.

 

Finally, several other elements of the original Master Plan require in-depth re-examination, possibly through separate or combined feasibility studies.  For example, in light of the current environment, it has become apparent that some areas of Stevens Hall need to be reassessed to determine that facility’s capability of supporting programs in the College of Education and Human Services. 

 

In addition to this, the Master Plan also targets the Health Center to move out of Keeling, thereby freeing up more space for the CSD Department.  The change in the timeline for Becht complicates this proposed relocation, and it should also be re-examined.

 

E.  The Mid-Term Plan (2009-2014)

      (Refer to Tables 5.2-2, Phases I & II for accompanying summary tables.)

 

The Mid-Term Plan will begin just after completion of the new Science and Technology Center and the subsequent demolition of the existing Peirce Science Center.  

 

Because so many of the recommended changes take place in the mid-term 2009-2014, this period has been split into two phases:  Mid-Term-Phase I (2009-2011) and Mid-Term Phase II (2011-2014).  The distinguishing characteristic of Phase I is the renovation of Becht.  As shown in the summary Table 5.2-2 and the Residence Hall Master Plan, students presently occupying Becht Hall will relocate to a newly constructed, suite style residence hall.  Faculty presently occupying the first floor of Becht Hall will be relocated to temporary offices in Ralston Hall during the renovation.

 

Phase II is distinguished by the relocation of a number of offices into Becht from Ralston after conclusion of the Becht renovation.  This relocation, incidentally, would facilitate the closer relationships among these offices that the traditional one-stop shopping concept would require.

 

Of particular note is that Admissions is presently located in a small residential-style building.  Current plans for the One-Stop Shopping concept in Becht Hall now includes space for Admissions.  In view of lost parking due to the siting of the new dining hall, the Admissions building is presently programmed for demolition with parking proposed to occupy the cleared area.  This will regain some of the parking stalls lost and also service the One-Stop Shopping activities in the renovated Becht Hall nearby.

 


F.  Long-Term Issues

 

The long-term aspects of the master plan generated a great deal of discussion by the committee as well as recommendations which diverged from the original plan.  Leading the way was discussion of Carrier. 

 

In the master plan, many of the administrative functions including the President’s office, the Provost’s office, the office of the Vice President for Finance and Administration, the office of Social Equity, and the Comptrollers Office would be relocated to Egbert Hall.  Egbert, in turn would relocate Student Affairs, Career Services, Counseling, and Housing to Becht.  From a practical perspective, Becht would not be available for renovation or relocation until at least 2010.  Beyond that though, moving administrative operations with minimal student contact to the center of campus and relocating student functions to the edge appeared to the committee to run counter to one of the primary tenets of the plan:  keeping “academic offices & support facilities . . . close to classroom space for their programs”.  A straightforward and cost effective solution suggests itself:  to keep these functions where they are.  The strategy of avoiding two moves or even one unnecessary move underlies this update and future facility plans.

 

Correspondingly, discussion of Public Safety, Facilities Planning, and Admissions currently located in small residential-style buildings on the edges of campus concluded that they served their customers best in their current locations.  Moreover these structures look to have extended useful lives, where the Master Plan recommended that they be demolished.  Of course, the perspective ten-years out may come back to the original Master Plan conclusion.  Nevertheless, the other key factor to consider for these buildings and residence halls that will eventually be vacated is the significant costs for demolition of these buildings.  Conversely we may be able to generate revenue to fund facilities needs by renting out residential properties.

 

Also under discussion in the long-term section was a permanent home for the Siler Children’s Learning Complex.  Current thinking has this relocating to a permanent site on the edge of campus which would address parking and vehicular safety concerns.  This would depend on the availability of funding to support a stand-alone facility.

 

Another long-term element of the master plan concerned the relocation of the Small Business Development Center (SBDC) and Computing Services out of Still Hall.  A pressing issue is the need to renovate Still Hall to accommodate space needs, remedy acoustic problems, and repair the HVAC system.  Current thinking has SBDC and other applied research functions moving to the Trinity Point facility.

 

Also at the north end of campus, are the Ceramics and Sculpture Laboratories.  These two functions have been housed in older buildings not originally intended for these uses, and the costs of upgrading the facilities to meet these new purposes have been prohibitive.  Rather than continuing to invest resources in buildings ill-suited to these functions, it is envisioned that they will move to a large open warehouse style building.

 

G.  The Long-Term Plan (2015-2019)

      (Refer to Table 5.2-3 for an accompanying summary table.)

 

As the Residence hall plan that follows suggests, when Ralston is no longer needed as swing space during the Becht Hall renovation, it may be scheduled for demolition.  At this time there are no plans for the use of this space.  The original Master Plan also suggests moving Health Services from Keeling and SBDC from Still.  Enrollment trends in these out-years will clarify whether this is necessary.

 

H.  The Revised Residence Hall Plan

 

Findings from the residence hall feasibility study that was conducted in April of 2001 by STV Architects point out the following:

 

1.      Student expectations for housing have changed significantly in recent years.

 

2.      Clarion’s six residence halls not longer offer the diversity of housing types and amenities to fulfill the needs of the student population.

 

3.      77% of the residence hall students expressed a preference in having single rooms or apartment style housing and expressed a willingness to pay a little more for this.

 

4.      New residence hall construction could negate the need for reconfiguration of the current residence halls.

 

Based on the feasibility study and on the decision to maintain the designed housing capacity of 2171 beds between the Reinhard Villages and the on-campus residence halls a long range plan for university housing was developed. Implementation of some of the early stages was accomplished in the fall of 2004.  Another factor that influenced the following plan was the PASSHE’s determination that upgrading, renovating, or replacing most of the residence halls on the campuses utilizing traditional State System bond financing would not be cost effective.  In order to address this situation and meet the demand a cooperative approach between the universities and an affiliated entity is being utilized.

 

FALL 2006

 

1.      Ralston Hall was taken off line as a residence hall

 

2.      Educational Talent Search was moved to the second floor of Ralston

 


SUMMER 2007

 

1.      University Relations moves from Alumni house to Ralston Hall

 

2.      Alumni and Haskell house demolished to make room for new suite style residence hall.

 

FALL 2007

 

1.      Construction will begin on two new suite style residence halls with a total of 360 beds. One will be located next to Ballantine at the present site of the Alumni and Haskell houses and the other between Chandler and Ralston Hall parallel and adjacent to campus drive.

 

2.      The project is to be funded by the Clarion University Foundation serving as the affiliated entity.

 

SPRING 2009

 

1.      Becht Hall is taken off line as a residence hall

 

2.      The suite style residence halls are open for occupancy.

 

3.      Approximately 40 rooms in other halls are converted from double rooms to single occupancy.

 

FALL 2009

 

1.      Approximately 40 rooms in other halls are converted from double rooms to single occupancy.

 

2010 AND BEYOND

 

1.      Ballantine Hall goes off line as a residence hall and is demolished to create space for the construction of two new suite style residence halls with occupancy of 350.

 

2.      The planning for the new residence halls includes the creation of approximately 240 single rooms by reassigning double occupancy rooms in the other halls.  This will allow the flexibility of converting these rooms back to double occupancy in the event of an enrollment increase.

 

3.      Becht Hall is converted one stop student services facility.

 

4.      Present E & G offices in Becht will move to Ralston.

 

5.      When renovations are complete and all E & G functions move from Ralston to Becht Hall, Ralston may be demolished.

 

I.  Food Service

 

Fall 2004

 

A feasibility study conducted in January 2003 revealed the need to renovate the Gemmell snack bar.  Students were dissatisfied with the long lines, limited seating space, variety of entrees.  The limited kitchen area prevented the food service from offering a variety of entrees without the proper equipment, and the area did not provide the space for additional equipment.  Taking into consideration all the above factors and the fact that more students chose to eat their meals at the snack bar instead of the main dining facility in Chandler, a decision was reached to renovate the snack bar area into a food court.   Renovation project was begun in December, 2003 and completed by August 13, 2004 for the opening of the fall semester. 

 

FALL 2006

 

Based on the cost to renovate Chandler Hall and to update the antiquated and inefficient food service equipment a feasibility study was commissioned to study the possibility of constructing a new dining facility. The study was concluded and a new dining hall utilizing the latest equipment and featuring a new way to serve and prepare meals for the students was proposed.  Due to the changing eating habits of our student body and the popularity of our food court in Gemmell it was decided that Chandler was oversized for our needs. This facility is a little over half the size of Chandler and will result in a considerable savings to our operations expenses, especially utilities and maintenance.  The site selected by the committee and supported by the study is the corner of Wood Street and Ninth Avenue. An RFP was issued to solicit proposals for design services for this facility and a firm was chosen in late November.

 

Spring 2007

 

1.      Design phase of new dining facility

 

FALL 2007

 

1.      Begin construction of new dining facility on the corner of Wood Street and Ninth Avenue.

 

SPRING 2009

 

1.      New dining facility opened.

 

2.      Chandler Hall demolished to make way for second phase of new suite style residence halls.


J.  Parking and the Master Plan

 

Currently there are 1689 parking spaces within the Main Campus area.  Individual lots on the campus are grouped into one of three use-permitting categories:  employee lots, commuter student lots, and resident student lots.  34 per cent or 568 spaces are assigned to commuter student parking. Resident student parking accounts for 510 spaces or 30 per cent.  Employee lots utilize 605 spaces or 36 per cent.

 

The concept of separating lots for commuting students and resident students was implemented in 1999.  The goal of this re-organization of lot assignments was to discourage resident students from utilizing their vehicles to travel throughout the campus.  This reduction in vehicle traffic was a goal identified in the master plan, thus reducing the potential vehicle-pedestrian conflict. 

 

A key recommendation in the April 1998 master plan regarding parking was to expand parking at the stadium and connect it with transportation which was subsequently provided by the Clarion Area Transit Service.  In addition to the 1,689 spaces on campus, the 442 stadium spaces are being utilized for long-term parking, allowing for the limiting of resident permit sales.  The result has been a consistent 85%-90% occupancy in residential lots, despite increasing demand for resident permits.  Over the past three years, the increase in demand for resident permits has required more and more students to park at the stadium.  In the year 2000, there were virtually no vehicles parking long term at the stadium.  In 2003, approximately 150 vehicles are consistently parked long-term at the stadium.  As an incentive to use the stadium, both commuter and resident students are offered a stadium permit free of charge, in comparison to the $100 per year fee for an on-campus permit.    Most of the 150 vehicles parked at the stadium are not there by choice, however. 

 

Master Plan Recommendations Implemented

 

1.      Growth Scenario projected 1,657 parking spaces by 2003.  Available space totals 1,689 though Lot P is leased space, with the lease to expire in 2011.

 

2.      The Plan called for reduced parking next to residence halls.  As a result, Lot 5 (Nair) has been converted to commuter parking and Nair/Wilkinson residents are parking in Lot P (Receiving) or Lot 15 (North of 322).

 

3.      The Plan recommended prohibition of campus parking for students living within one-half mile of campus.  As a result, approximately 25% of off-campus students have purchased commuter permits (1,000 out of 4,000).

 

Remaining Issues

 

1.      There is still a widespread feeling that there is not enough parking “on campus”.  Based on the industry standard for available parking of 10%, it would appear that the Clarion campus has adequate parking however there are shortages depending on the time and type of permit.

 

2.      The new Science and Technology Center will cause a major, though temporary reduction in parking.

 

3.      The Reinhard Villages will likely change traffic patterns significantly, but we do not know how or how much.  It has already changed the bus routes, thereby parking needs.

 

4.      We continue to implement the fringe parking solution, moving student parking and some parking in general to the edge of campus. 

 

5.      The current proposal to solve issues one through four would be to build a parking deck on the site of Campbell Hall.  This function will need to be self-sufficient however, and funding models to accomplish this are currently being considered.

 

 

 

 