Clarion University Construction Update -- 4/13/08
|
|
Campbell
Hall Demolition and South Campus Parking Lot |
|
The
demolition is complete and backfilling operations are underway. Half of
the future parking lot, across from Gemmell Complex, has been backfilled to
the bottom of the parking lot sub base. Removal of trees necessary to
install the parking lot will be completed next week. |
|
|
|
Dining
Hall |
|
Roofing is complete on the north side of the Dining Hall and has
started on other sides of the building. Brickwork and insulation is
being installed over the concrete blocks on the north and west sides of the
building. Pedestrian/Vehicular traffic and safety: While the road between Carrier and the
new dining hall is now open, there continues to be
work on the roof and upper floors near sidewalks and roads.
Construction vehicles will also be entering and leaving the job site to
transport materials. Please use caution near the jobsite. |
|
|
|
|
|
General construction continued throughout the
project. Placing the concrete floor sections continued. Plumbing,
ductwork, and the electrical system installation continued on the second and
third floors. Construction of the concrete steam trough continued with
the completion slated for May. Pedestrian/Vehicular traffic and safety: Trenching is
being dug in the area of the Science-Technology construction site in the
future to allow workers to connect electric, sewer, water and communications
lines to the site. Please use extra care around excavation and normal
pedestrian traffic paths near this site. |
|
|
|
On-Campus
Residences |
|
Framing
continued on both buildings this week. We see work on the top stories
now and the beginnings of a roofline. Installation of the sanitary
sewer lines for Building #4 (near Ralston) is expected to resume next week
and progress is being made on all utilities for the buildings. Pedestrian/Vehicular traffic and safety: Trenching is
being dug in the area of both sites and some roads may be temporarily blocked
to access the job or utilities. Please use extra care around excavation
and normal pedestrian traffic paths near this site. |
|
|
Other Pedestrian/Vehicular traffic and safety issues: Orientation
will be using Lot H and |
|
|
|
|
|
Photos and other information on projects provided by Dave Fagan
and Joe Brinkley. |
|
More
information about construction can be found in the minutes of the regular
meetings of the Facilities Planning Committee and Parking Committee, provided
below:
Facilities
Planning:
http://www.clarion.edu/admin/facilitiesmanagement/planning/facplancomm.shtml
Naming
opportunities are available for projects. For additional information about
supporting Clarion’s building program, please contact Rika Beckley,
associate vice president for development, at 814-393-2572.