|
|
Campbell
Hall Demolition and South Campus Parking Lot |
|
Scrap steel
continued to be removed this past week and will continue next week.
Demolition of Campbell Hall concrete foundations began this past week and
will continue until removed. Backfilling of the building cavity with
the crushed brick and block building block follows the foundation removal
and will provide a support for the South Campus Parking
Lot. Pedestrian/Vehicular
traffic and safety:
Demolition by nature can be hazardous despite efforts to contain
debris. Please use extra caution and do not walk or drive near
demolition sites. | |
|
|
Dining
Hall |
|
Roofing is
complete on the north side of the Dining Hall and will begin on other
sides of the building as weather conditions permit. Brickwork is
being installed over the concrete blocks. Plans for the
Starbucks to be located in the building are being reviewed. Exterior
finishes and roofing have been chosen, except for glass which will be LEED
(energy efficiency standard) compliant. We will soon begin planning
for the demolition of Chandler Dining Hall and the relocation of utility
lines to facilitate the next phase of on-campus student
residences. Pedestrian/Vehicular
traffic and safety:
The road
between Carrier and the new dining hall may be closed and the front entrance of Carrier
locked intermittently while the roof is
installed in order to
preclude pedestrian hazards from falling debris. A
trench for electrical lines will be dug across lot H and the walkway from parking
lot 6 and lot H to Carrier
may be obstructed in early April. Those parking in Lot H and Lot 6
should use the steps east of Lot
H. | |
|
|
|
|
Placing the
concrete floor sections continued and the last concrete roof section has
been placed. Installation of the exterior steel curtain wall
support, piping, HVAC ductwork, and electrical conduits
continued. Major pieces of equipment are on-site and will be
set as the supports are completed. Installation of the concrete
steam trough, which connects the existing steam tunnel, began this past
week. Pedestrian/Vehicular
traffic and safety:
Trenching is being dug in the area of the Science-Technology construction
site in the future to allow workers to connect electric, sewer, water and
communications lines to the site. Please use extra care around
excavation and normal pedestrian traffic paths near this
site. | |
|
|
On-Campus
Residences |
|
Framing and
sheeting continued on both buildings this past week. Preparations
are underway to connect the buildings to the campus electrical system and
expected to complete this summer. The contractor continues to work
added hours and personnel as needed to make up any weather related lost
time. | |
|
Other
Pedestrian/Vehicular traffic and safety
issues:
Orientation will be using Lot H and | |
|
| |
|
Photos
and other information on projects provided by Dave Fagan and Joe
Brinkley.
| |
Student
opt-out instructions for students are provided in
attachment.
More information about construction
can be found in the minutes of the regular meetings of the Facilities Planning
Committee and Parking Committee, provided below:
Facilities Planning:
http://www.clarion.edu/admin/facilitiesmanagement/planning/facplancomm.shtml
Naming opportunities are available
for projects. For additional information about supporting Clarion’s building
program, please contact Rika Beckley, associate vice president for development,
at 814-393-2572.