Campbell Hall Demolition and South Campus Parking Lot

 

Campbell Hall demolition has basically been completed.  As possible scrap is being recycled and reused, some possibly as fill for the construction of the new parking lot to be constructed on the siteDebris is being removed and the site prepared for the parking lot.  Approval of the parking lot project has been requested from the University Council of Trustees and the State System Board of Governors.

 

Dining Hall

 

Steel roof trusses and archways have been installedA significant amount of the blocks have been laid on the north side of the exterior, but  because of the continuing work in this area, expanded scaffolding will keep the road between Carrier and the new dining hall restricted to one lane.  Entry to lot 5, lot 6 and lot H should be made from Wood Street.

 

Science-Technology Building

 

Steel work and floors for the upper stories of the building are nearly complete.  We now see wall framing work which will accommodate installation of the exterior wall.  

 

On-Campus Residences

 

The on-campus residence south of Chandler Dining Hall has shown the most progress.  Here you will see the exterior framing ready for future installation of windows.  For both residence sites, with more favorable weather, we expect contractors to make up weather-related delays.

 

Naming Opportunities Available

 

Naming opportunities are available for projects. For additional information about supporting Clarion’s building program, please contact Rika Beckley, associate vice president for development, at 814-393-2572.

 

Paul Bylaska

Vice President for Finance & Administration

218 Carrier

Clarion University

Clarion, PA 16214

pbylaska@clarion.edu

TEL:  (814) 393-2240

FAX: (814) 393-1826