Project No. CL671-
Parking Lot –
CJL Engineering
#08-010
Date of Meeting –
May 6, 2008
Date of Report –
May 7, 2008
Attendees:
David Fagan -
Ryan Miles - Terra
Works - 814-226-0702 -
Nick Corcetti - RJ Corcetti
Corp. - 814-226-8262
Brian Steinman - S
and R Corp. - 814-229-3746
Jason Kiely - Francis J. Palo - 814-226-9361
Don Hager - Hager
Paving - 814-764-5080 -
Joe Burns Jr. -
Fred L Burns, Inc. - 814-226-4582 - flburns@choiceonemail.com
Don Liedl - Glenn O. Hawbaker -
814-371-2005 -
Todd Glenn - Glen
O. Hawbaker -
814-591-9424 -
Dennis Hepler - Horizon Construction - 724-376-4473 - horizon@certany.net
Bruce Harkleroad - Rural Valley Construction - 724-354-2677
David Duray - CJL
Engineering - 814-536-1651 - dduray@cjlengineering.com
A Pre-Bid Meeting
was held at the project site at 10:00 a.m. to review the project, bid
requirements, scope and project schedule.
The following items were discussed.
1.
All
technical questions should be directed to Dave Duray at CJL Engineering. All administrative questions should be
directed to
2.
Any
request for substitution must be made in writing with the appropriate
documentation prior to five days before the bid date.
3.
After
the bid opening the Contractor must supply equipment/materials from the
manufacturers listed in the Contract documents.
4.
It was noted
that this is a prevailing wage project.
5.
6.
It was
noted that the construction cost estimate for the General Contract is $800,000
to $820,000 and that for the Electrical Contract is $60,000 to $80,000.
7.
The bid
forms must have the same signature on them and they must be notarized.
8.
The bid
is required to include a bid guaranty in the amount of 5% of the bid.
9.
The
Contractors must use the Bid bond form included in the bid package and it must
be dated the same date or later than the bid.
10.
A
complete bid package is included with the bid documents.
11.
12.
13.
It was
noted that the General Contractor will be the lead Contractor and will
coordinate the schedule with the Electrical Contractor.
14.
It was
noted that the permitting authority is the PA Department of Labor & Industry and
that the Contractor does not need to apply for any permits but must notify them
for inspections.
15.
It was
noted that the Contractor is required to perform a PA One Call in writing and
copy the University.
16.
It was
noted that water and power is available from adjacent University
facilities. The Contractor is responsible
for their bathroom facilities.
17.
18.
The normal
working hours for Contractors is 7:00 a.m. to 3:00 p.m. but that can vary. The Contractor can work more than 40 hours
per week.
19.
Payroll
certifications are due at the time the Application for Payment is submitted.
20.
The
Date of Completion is 90 days from the Notice to Proceed.
21.
Project No. CL671
Project Name:
Parking Lot –
Bids Due: 3:00 p.m., May 28, 2008
To: Prospective Bidders
This Addendum forms
a part of the contract documents and modifies the original Contract documents
dated April 21, 2008. Please acknowledge
receipt of this addendum in the space provided on the Bid Proposal Form.
This addendum
consists of two (2) pages with attachments and covers modifications to:
Pre-bid Conference
The Pre-bid meeting time should read 10:00 a.m. rather than 1:00 p.m.
The Bid opening date and time has been changed to 3:00 p.m. May 28, 2008.
1. Section 01010 “Summary of Work”, Paragraph 1.7 Contractor Use of Premise; Item A, add the following paragraph 3:
3.
2. Sections 01027, 01035, 01200, 01300, 01400, 01600, 01631, 01700, 01740; The footer should read CL671 Parking Lot Payne to McEntire.
1. Section 02300 “Earthwork”, Paragraph 3.6 Field Quality Control; Item A and C shall be modified to read as follows:
A. Testing Agency: Contractor shall engage a qualified independent geotechnical engineering testing agency to perform field quality-control testing.
C. Tests shall be performed at a minimum of 50 ft. increments or as directed by the Owner.
2. Section 02740 “Bituminous Paving”, Paragraph 3.9 Compaction; Add the following paragraph:
H. The Contractor shall engage a qualified independent testing agency to perform field quality-control density testing. Tests shall be performed at a minimum of 50 ft. increments for each pass of the paver randomly distributed over the width of the mat or as directed by the Owner.
3. Add Section 02970 “Raingarden” (attached).
1. Add drawing C-105 “Rain Garden Plan & Details” to the Drawing Index.
1. The note referring to the removal of the parking meter shall be revised to read as follows:
“Remove parking meter and sandblast the associated stall lines (3).”
Drawing C-101 Site Plan
1. This sheet is to be deleted in its entirety. Substitute revised drawing C-101 “Site Plan” attached to this addendum dated May 15, 2008 into the Contract Documents. Revisions to this drawing include, but are not limited to the following:
a. Add the rain gardens.
b. Revise the retaining wall.
c. Remove the landscape area on the lower parking lot and replace with additional parking spaces.
d.
Add “General Notes” and other notes concerning
1. This sheet is to be deleted in its entirety. Substitute revised drawing C-102 “Grading Plan” attached to this addendum dated May 15, 2008 into the Contract Documents. Revisions to this drawing include, but are not limited to the following:
a. Revised grading at Rain Garden 1, 2, and 3.
b. Revised grading at the new parking stalls on the lower lot.
Drawing C-103 Utility Plan
1. This sheet is to be deleted in its entirety. Substitute revised drawing C-103 “Utility Plan” attached to this addendum dated May 15, 2008 into the Contract Documents. Revisions to this drawing include, but are not limited to the following:
c. Revised storm sewer alignment.
d. Added inlets.
e. Changed inlets to manholes.
Drawing C-104 Erosion & Sedimentation Control Plan
1. Add the following notes:
5. The soil surface under the 30-inch storage pipes and aggregate in the lower parking lot shall be scarified to promote infiltration.
6. Excavate the rain gardens to proposed invert depth and scarify the existing soil surface. Do not compact in-situ soils. Do not compact constructed soil mix or shredded hardwood bark.
Drawing C-105
1. Add this sheet.
Drawing C–201 Construction Details
1. Revise the backfill material for the manhole from ODOT Type 304 Crushed Aggregate Compacted in 6” Layers to AASHTO No. 57 Crushed Aggregate Compacted in 6” Layers
Drawing C–202 Construction Details
1. This sheet is to be deleted in its entirety. Substitute revised drawing C-202 “Construction Details” attached to this addendum dated May 15, 2008 into the Contract Documents. Revisions to this drawing include, but are not limited to the following:
a. Revised cement sidewalk detail.
b. Added landscape area typical section.
c. Added storm manhole detail.
Drawing C-203 Construction Details
1. This sheet is to be deleted in its entirety. Substitute revised drawing C-203 “Construction Details” attached to this addendum dated May 15, 2008 into the Contract Documents. Revisions to this drawing include, but are not limited to the following:
a. Revised segmental wall typical section to include slope.
b. Revised storm water storage pipe typical detail.
c. Revised segmental retaining wall profile.
Drawing C-204 Construction Details
1. Revised Sequence of Construction Note #10 to state:
Install all utilities. The soil surface under the 30-inch storage pipes in the lower parking lot shall be scarified to promote infiltration. Install filter bags in the new storm inlets as shown on the Drawing.
2. Added Sequence of Construction Note #12:
12. Construct rain gardens. Excavate rain
gardens to proposed invert depth and scarify the existing soil surface. Do not
compact in-situ soils. Do not compact constructed soil mix
or shredded hardwood bark during installation. Refer to rain garden
specification for step-by-step installation procedure.
Drawing C-301 Storm & Sanitary Sewer Profiles
1. This sheet is to be deleted in its entirety. Substitute revised drawing C-301 “Storm & Sanitary Profiles” attached to this addendum dated May 15, 2008 into the Contract Documents. Revisions to this drawing include, but are not limited to the following:
a. Revised profile.
Drawing SE1 Lighting Plan
1. This sheet is to be deleted in its entirety. Substitute revised drawing SE1 “Lightining Plan” attached to this addendum dated May 15, 2008 into the Contract Documents. Revisions to this drawing include, but are not limited to the following:
a. Wiring size to upper parking lot pole lighting fixtures shall be changed to 3#6 & 1#10 ground in 1” conduit instead of 3#8 & 1#10 ground in 1” conduit.
b. Locate (1) ‘B’ type pole lighting fixture as indicated on revised drawings.
c. Remove pull box indicated at existing parking lot lighting fixture as indicated on revised drawings.
d. Replace all existing circuiting with new (including conduit) to three new Campus King luminaries.
e. Extend all concrete encasements to 5’-0” beyond edge of all paved and concrete areas as indicated on revised drawings.
Drawings








End of Addendum #2