DATE
OF ISSUE:
April 15, 2008
NOTICE
TO CONTRACTORS
![]()
Sealed proposals will be received at
![]()
Brief
Description: The Electrical
Contractor is the single prime contractor for this project. The Electrical Contractor’s work includes all
work for the project. The work includes,
but is not necessarily limited to the following:
Demolition of existing
diesel engine generator, fuel tank, and cap existing exhaust pipe. Remove
exhaust pipe in its entirety and patch all openings with watertight materials.
The existing transfer switch and panelboard and circuiting shall remain. Furnishing and installing of all new exterior
pad mounted generator in sound attenuation weatherproof housing, fuel tanks,
transformers, automatic transfer switches, panelbaords, conduit, and feeders
and circuiting. Provide exterior
concrete generator mounting pad along with all associated excavating,
trenching, and back filling. Also
included is new concrete service walkway around the generator as indicated on
the drawings. Provide all materials
necessary to connect remote generator status panel with existing campus wide
Johnson Controls Metasys system to indicate trouble signal (generator did not
start) to maintenance, public safety and boiler house monitors. The Contractor shall provide all anchoring
bolts and materials necessary to secure the generator and its weather proof
housing to the generator pad.
University Contracting Officer: The University Contracting Officer for
this Project is:
W.
Finance
and Administration
Opening Date and
Time: 2:00 P.M., May 13, 2008
Pre-bid
Conference: A pre-bid
conference will be held on Tuesday April 29th , 2008 at 10:00 A.M. in the McEntire Conference Room, Clarion, PA. Directions to campus are available by checking
our website, www.clarion.edu or contacting
the University Project Manager, Dave Fagan, at 814/393-2453. The pre-bid meeting will be the only site
visit conducted by the University and the only review of plans and
specifications. All Contractors are
urged to attend.
Contract Nos./Cost
Range: CL-667.4 – Electrical:
$160,000
to $180,000
MBE\WBE REAA
Participation Levels: CL-667.4
– Electrical: $ 20,000 to $
24,000
Bid Guaranty: 5% of bid
amount
Proposal
Period: 60 calendar days allowed from Bid Opening
until Award of Contract
Contract
Approval Period: 120
calendar days allowed from Bid Opening until Notice to Proceed
Proposed Date of Completion: 180
calendar days from Date of Notice to Proceed.
Liquidated
Damages: The
Contractor shall pay to the System, as liquidated damages and not as a penalty,
the amount of $ 200.00 for each
and every calendar day beyond the specified number of calendar days of
completion.
Professional: CJL
Engineering
Moon
Plans Cost/Contact:
$65 nonrefundable, by
check payable to
Contact for Bid and
Specification Information:
Bidders'
Services: Plans
and specifications are available for review at McEntire Maintenance,
CONTRACTUAL
REQUIREMENTS
Bid Guaranty:
It has been determined by the University that for this work a bid
guaranty is required. As a bid guaranty,
each Proposal must be accompanied by a Certified Check, Bank Cashier's Check or
BID Bond. If a Bid Bond is submitted, it must be in the amount of 5% of the contract
bid proposal amount, and it MUST be submitted on the System furnished Bid Bond Form. FAILURE
to submit a bid guaranty; or, if the Bid Bond is used as a Bid Guaranty,
failure to submit the completed (all signatures and seals) System-furnished Bid
Bond Form may result in the rejection of the Bid Proposal as non-responsive.
Performance and Payment Bonds:
Performance
and Payment Bonds in the amount of the contracts are required for work
performed under the contracts awarded for this project. Bond requirements are contained in Rider
F-Contract Bonds of the System's Standard Form of Agreement for Facilities
Projects.
Nondiscrimination
The State
System of Higher Education is an equal employment opportunity agency with
special nondiscrimination requirements, as published in the Commonwealth
Contract Compliance regulations 22 PA Code Chapter 509 and in the State System
of Higher Education Contract Compliance Requirements contained in the bid
proposal form.
Debarred Contractors:
Contractors
currently under suspension or debarment by the Commonwealth, any other state,
or the federal government are not eligible for an award of contract for this
project. Additionally, contractors
should not contract with or employ subcontractors or individuals that are currently
under suspension or debarment by the Commonwealth or the federal
government. A current list of suspended
or debarred contractors is available by contacting the Department of General
Services, Office of Chief Counsel,
Product Substitution:
Any
product substitution requests shall be submitted to the design professional a
minimum of ten (10) calendar days prior to the date set for receipt of bid
proposals. Those product substitutions
that are accepted will be published in an addendum. After the bid opening, product substitutions
will be considered only for those conditions listed in Section 01631-Product
Substitutions.
MBE\WBE Participation:
The
Contractor must demonstrate that he has complied with the State System of
Higher Education Draft Regulation Minority Business and Women Business
Enterprise (MBE/WBE) in facilities projects, as outlined in the bid proposal
form, in the preparation and submission of their bid proposals.
All
bidders must directly contact certified MBE/WBE subcontractors and/or suppliers
to request quotes. Bidders must solicit
MBE/WBE firms in a timely manner to allow sufficient time for a response, in
the same manner bidders solicit from other subcontractors and suppliers. In order
for a
solicitation to be considered a qualified proactive solicitation, it must
contain the following minimum information:
1. The solicitation must be written, and on
the bidder's business letterhead
2. The date of solicitation indicated
3. The name and address of MBE\WBE firm
solicited
4. The project name and number
5. A listing of the specific equipment,
materials and/or supplies, including appropriate quantities, that the bidder
intends to purchase or lease. The scope
of work for any subcontract work should be clearly outlined.
6. Instructions as to where the plans and
specifications (if not attached) are available to be reviewed.
Information regarding the availability
of certified Minority and Women Business Enterprise (MBE/WBE) may be obtained
form the