Construction Updates are provided below.
|
|
Clarion Campus – Science-Technology Building - Science-Technology Center WebCam |
|
Spring temperatures, and associated ground conditions will impact outside activity, such as ground restoration and installation. Inside activities continued, however, with painting, installation of copper wall surfaces and lab furnishings and installation of the ceiling grid and work on the stair tower walls. Following closely are the HVAC, plumbing and electrical contractors most evident with installation of the light fixtures as the ceiling grid was installed. |
|
|
|
Venango Campus – Venango Pond |
|
While weather conditions have delayed the final touches to this project, work done on the pond t have allowed resumption of normal wintertime use.
|
|
|
|
Venango Campus – Rhodes/Davis Locker Room |
|
Final work is progressing in the locker room as materials have arrived for installation.
|
|
|
|
Venango Campus – Residence Suites |
|
Walls are complete and being insulated. Roof trusses are also going up quickly enabling roofing in the near future as weather allows.
|
|
|
Photos and information on projects provided by Dave Fagan and Joe Brinkley. WebCams provided by University Relations. |
|
More information about construction can be found in the minutes of the regular meetings of the Facilities Planning Committee and Parking Committee, provided below:
Facilities Planning: http://www.clarion.edu/32034/
Parking: http://www.clarion.edu/57809/
Naming Opportunities Available
Naming opportunities are available for projects. For additional information about supporting Clarion’s building program, please contact Chuck Desch, Development Officer, at 814-393-2572.
Paul Bylaska
Vice President for Finance & Administration
218 Carrier
Clarion University
Clarion, PA 16214
TEL: (814) 393-2240
FAX: (814) 393-1826