Projects are removed from this list periodically when construction is complete. Every attempt has been made to ensure accuracy and reliability of the data contained in the information provided on this web page and attachments hereto. In addition, information is constantly being added and/or updated. Clarion University, the author of these pages or any contributors thereto are not responsible for errors in the materials provided herein. Although every reasonable effort has been made to ensure that the information on this page was correct at the time of publication, all materials provided on the Web are provided "as is" with no warranties of any kind. Questions concerning or correction to the information provided herein should be directed to Ruth Wolfgong, Contract Specialist at 814/393-2365 or rwolfgong@clarion.edu )
CONTRACT AWARDS |
Project No. |
Project Name/Description |
Award Date |
Contractor |
Amount |
|
CL-684 |
Boiler Plant Renovation |
CL684.2 Renick Brothers |
$1,803.000.00 |
|
|
CL-627 |
Gemmell HVAC Renovation |
CL627.1 Francis J. Palo, Inc. CL627.2 Rabe Environmental CL627.4 Climax Electric |
$ 54,500.00 $151,200.00 $ 31,960.00 |
|
|
CL-657 |
Frame & Rhoades Hall Facility Locker Room & Restroom Upgrade |
CL657.1 Michael Lukasiak CL657.2 Central Heating & Plumbing CL657.3 Enders Plumbing CL657.4 Cox & Kanyuck |
$226,000.00 $ 30,425.00 $ 85,500.00 $ 66,800.00 |
|
|
CL-660 |
Still Hall Data Emergency Generator |
CL660.4 Bronder Technical Services |
$154,465.00 |
|
|
CL-663 |
Gemmell Chiller Replacement |
CL663.2 Renick Brothers |
$212,322.00 |
|
|
CL-666 |
McEntire HVAC Renovation |
CL666.2 Central Heating & Plumbing |
$ 97,831.00 |
|
|
CL-667 |
Keeling Window Replacement |
|
CL667.1 Glass Erectors, Inc. |
$ 42,828.00 |
|
CL-668 |
Davis Roof Replacement |
CL668.1 Strongland Roofing |
$133,900.00 |
|
|
CL-671 |
Payne to McEntire Parking Lot |
CL671.1 Glenn O. Hawbaker CL671.4 Tech Services |
$728,999.00 $ 78,400.00 |
|
|
|
||||
|
CL-678 |
Chandler Dining Hall Demolition |
CL678.1 Ritter & Paratore |
$229,000.00 |
|
|
CL-697 |
Open Ended Asphalt Repair |
CL697 Hager Paving, Inc. |
$50,000 per work order $250,000 per yr. max. |
|
|
|
||||