2009-10-30

 

 

Construction Update - 10/30/09

 

 

 

Construction continues around the new Science Technology Building, and the south entrance remains closed to pedestrian traffic.  Minor repairs are being made on Eagle Commons and additional lighting is being installed between Eagle Commons and Carrier.  Please use extra caution, slow your vehicle and watch for pedestrians while in these areas or when construction vehicles are in transit.

 

 Science Tech 10-30-09

 

Clarion Campus – Science Technology Construction

The south walkway on the Greenville side of the Science & Technology Center was installed this week. Separately the top soil is being spread on both the Greenville and Harvey sides of the new building.  Outside construction activities are expected to continue between the inclement weather spurts. 

 

 

Peirce Demo 10-30-09 

Clarion Campus – Peirce Demolition

Top soil and sub grade material is being moved from the Greenville side to the Harvey side of the Science & Technology Building.  Grading and earth moving activities are expected to continue depending on the weather.

 

 

Chandler Demo 10-30-09 

Clarion Campus – Chandler Demolition

Fine grading, seeding, and mulching was quickly finished this week to beat possible inclement weather.  Asphalt patching remains with area roads blocked to traffic until patching is complete. 

Photos and information on projects provided by Dave Fagan and Jim Stockman.  Please feel free to share this E-Mail with friends of Clarion University who may not have regular updates on the Clarion campus. 

 

More information about construction can be found in the minutes of the regular meetings of the Facilities Planning Committee and Parking Committee, provided below:

 

Facilities Planning:      http://www.clarion.edu/50397/?draft-preview=true

 

Parking:                       http://www.clarion.edu/57809/

 

Naming Opportunities Available

 

Naming opportunities are available for projects. For additional information about supporting Clarion’s building program, please contact Chuck Desch, Development Officer, at 814-393-2572.

 

Paul Bylaska

Vice President for Finance & Administration

218 Carrier

Clarion University

Clarion, PA 16214

pbylaska@clarion.edu

TEL:  (814) 393-2240

FAX: (814) 393-1826